We are carrying out underground power cable installations along La Trobe Street (see map). These works involve trenching on the northbound side of the road, between Spencer Street and King Street. The majority of construction works will take place between September 2025 and early November 2025, scheduled during the hours of 9:30am to 3:00pm.
Weekly update on progress of works – 2 October
Day works continue from King Street end of La Trobe Street and crews are making steady progress on the underground works, working their way back towards Spencer Street. Progress this week has been steady, with some additional time required for non-destructive digging around existing underground assets.
Works
We are completing underground power cable works on La Trobe Street, between Spencer Street and King Street as per the map below. The majority of construction works will be completed between September 2025 and November 2025.
Traffic Impacts
What to expect
Work area stage 1
Work area stage 2
Work area stage 3 (night works)